NewBuildDwell 1. Notification of Commencement
NewBuildDwell 2. Inspection at foundation excavation
NewBuildDwell 3. Inspection at DPC level
NewBuildDwell 4. Inspection at floor structure
NewBuildDwell 5. Inspection at roof structure
NewBuildDwell 6. Inspection at 1st fix MEP and insulation and fire ratings
NewBuildDwell 7. Inspection at internal partitions and boarding out
NewBuildDwell 8. Inspection at 2ndfix MEP
NewBuildDwell 9. Inspection at 95% completed fire doors and smoke alarms
NewBuildDwell 10. Notification of Completion
Installer certificates required: Electrical, Unvented cylinder, Gas appliance, HETAS, Air Test, Carbon Calcs and EPC, Sound Test, Water Calculation
File Photo required: Damp proof membrane to ground floor slab